Processing & Timeline
Staff Review Entitlement Process
- Submit Application and Fee to the City
- Review by the Planning Division staff to determine if the Application is complete (2 to 5 days)
- Environmental Review/CEQA
- 1 to 5 days if the project causes no environmental impacts and exempt per CEQA
- 45 days if there are impacts which can be mitigated through a mitigated negative declaration
- 90 to 180 days if an EIR is required
- Analysis by City Staff (5 days)
- Final Approval (5 to 10 days if exempt per CEQA and/or EIR is not required)
Design Review Entitlement Process
- Submit Application and Fee to the City
- Review by the Planning Division to determine if the Application is complete (15 to 30 days)
- Environmental Review /CEQA
- 1 to 5 days if the project causes no environmental impacts and exempt per CEQA
- 45 days if there are impacts which can be mitigated through a mitigated negative declaration
- 90 to 180 days if an EIR is required
- Notification of the Public and Staff Analysis (30 days)
- Presentation of the Analysis to the Planning Commission
- Final Approval (45 to 60 days total if an EIR is not required)
Conditional Use Permit (CUP) Entitlement Process
- Submit Application and Fee to the City
- Review by the Planning Division to determine if the Application is complete (15 to 30 days)
- Environmental Review/CEQA
- 1 to 5 days if the project causes no environmental impacts and exempt per CEQA
- 45 days if there are impacts which can be mitigated through a mitigated negative declaration
- 90 to 180 days if an EIR is required
- Notification of the Public and Staff Analysis (30 days)
- Presentation of the Analysis to the Planning Commission
- Approval (60 to 90 days if an EIR is not required)
- Design Review Process may also be required and will be processed concurrently with CUP.